Umm Al Quwain desalination plant

Projects
Project:
Umm Al Quwain desalination plant
Operator:
ACWA Power
Water balance:
1377630 [m³H2O]
Estimated annual value:
25000 [m³H2O]
Technical description:
Physical variable:
Volume
Meters:
1
Parameterization:
Exante Factor:
1 [m³H2O/m³]

The Plant along with the associated intake & outfall facilities shall be developed to produce 150 MIGD (682,000 m³/day) of desalinated water. The project shall be located at a coastal site in the Emirate of Umm Al Quwain along the border of Emirate of Ras Al Khaimah. Disclosure: This is a DEMO project.

Technical information
Methodology:
Balances hídricos N/A
Standard:
No registrado N/A
End of monitoring:
12/31/2044
Start of monitoring:
1/1/2023
Length of credit period (years):
12
MRV Description

Water productions is remotely and continuously measured monitored, and then cross-checked with third parties information.

SDG 6: Clean water and sanitation SDG 11: Sustainable cities and communities SDG 12: Responsible consumption and production SDG 13: Climate action

No mentions have been found on the NDC.

0xDadCc01262Ab1a635Ddfc2a8dBc4416eB685a3C2

m³H2O
21,872
Water balance [m³H2O]
Volume [m³]
21,872
# Medidores
1
Monitored quantity [m³]
Information backed on blockchain
Day Meter Blockchain Calculated
6/6/2025 Umm Al Quwain Meter
cbe5744a527f6433b3891180eace6ce0dc0e64ddb3916cd43887cd1b7406f8ed
cbe5744a527f6433b3891180eace6ce0dc0e64ddb3916cd43887cd1b7406f8ed
6/5/2025 Umm Al Quwain Meter
bc799e76df518aef63fc30f6fd714233ede021d0d358917705669a72736fdd6d
bc799e76df518aef63fc30f6fd714233ede021d0d358917705669a72736fdd6d
6/4/2025 Umm Al Quwain Meter
d1deef9abd7aaa5da7779881677642ac0fd493a8f1009e773044f62425ccbc9c
d1deef9abd7aaa5da7779881677642ac0fd493a8f1009e773044f62425ccbc9c
6/3/2025 Umm Al Quwain Meter
bc5736d9be9e41eba904e8e03e03fc0aab2cb2ae34b7f6429d5639696d5463e1
bc5736d9be9e41eba904e8e03e03fc0aab2cb2ae34b7f6429d5639696d5463e1
6/2/2025 Umm Al Quwain Meter
c774818c2021839cfec315dc0aad9689ca1286e07cdc61b67b445b078bc0f2fc
c774818c2021839cfec315dc0aad9689ca1286e07cdc61b67b445b078bc0f2fc
6/1/2025 Umm Al Quwain Meter
a0fc6c870baeaa43f185cd05764677f7d7418e442fd84c2a0177d6380cbdc333
a0fc6c870baeaa43f185cd05764677f7d7418e442fd84c2a0177d6380cbdc333
5/31/2025 Umm Al Quwain Meter
6ca17cb9c1d22b6ddbe5345628e6181fdcad49a137959121226f35ab22ef5a08
6ca17cb9c1d22b6ddbe5345628e6181fdcad49a137959121226f35ab22ef5a08
Meters
ID Project Name Data source Type Output unit (Material) Frequency monitoring Time zone Actions
ID Project Name Data source Type Output unit Frequency monitoring Time zone Actions
62 Umm Al Quwain desalination plant Umm Al Quwain Meter API Cliente Primario
Volume
1 hora
Periódica
Asia/Dubai
Verifications
Creator Project Token Start End Type Status Emissions reduction Certificate Actions
Creator Project Token Start End Type Status Emissions reduction Certificate Actions
UAQ-WD
ACWA Power
H2O 6/1/2023 6/30/2023 Semi-automática En progreso 95,305.71 m³H2O
UAQ-WD
ACWA Power
H2O 7/1/2023 7/31/2023 Semi-automática Confirmada 100,289.31 m³H2O
UAQ-WD
ACWA Power
H2O 4/1/2024 4/30/2024 Semi-automática En progreso 96,538.13 m³H2O
UAQ-WD
ACWA Power
H2O 5/1/2024 5/31/2024 Semi-automática En progreso 89,079.61 m³H2O
UAQ-WD
ACWA Power
H2O 6/1/2024 6/30/2024 Semi-automática En progreso 89,148.56 m³H2O
UAQ-WD
ACWA Power
H2O 7/1/2024 7/31/2024 Semi-automática En progreso 91,815.82 m³H2O
UAQ-WD
ACWA Power
H2O 8/1/2024 8/31/2024 Semi-automática En progreso 82,711.88 m³H2O
UAQ-WD
ACWA Power
H2O 9/1/2024 9/30/2024 Semi-automática En progreso 85,737.22 m³H2O
UAQ-WD
ACWA Power
H2O 10/1/2024 10/31/2024 Semi-automática En progreso 70,584.12 m³H2O
UAQ-WD
ACWA Power
H2O 11/1/2024 11/30/2024 Semi-automática En progreso 85,995.1 m³H2O
UAQ-WD
ACWA Power
H2O 12/1/2024 12/31/2024 Semi-automática En progreso 91,695.69 m³H2O
UAQ-WD
ACWA Power
H2O 1/1/2025 1/31/2025 Semi-automática En progreso 35,550.47 m³H2O
UAQ-WD
ACWA Power
H2O 2/1/2025 2/28/2025 Semi-automática En progreso 77,988.71 m³H2O
UAQ-WD
ACWA Power
H2O 3/1/2025 3/31/2025 Semi-automática En progreso 90,824.12 m³H2O
UAQ-WD
ACWA Power
H2O 4/1/2025 4/30/2025 Semi-automática En progreso 96,257.04 m³H2O
UAQ-WD
ACWA Power
H2O 5/1/2025 5/31/2025 Semi-automática En progreso 98,108.91 m³H2O
Last 7 hashes of readings backed on the Blockchain
Day Meter Blockchain Calculated
6/6/2025 Umm Al Quwain Meter
cbe5744a527f6433b3891180eace6ce0dc0e64ddb3916cd43887cd1b7406f8ed
cbe5744a527f6433b3891180eace6ce0dc0e64ddb3916cd43887cd1b7406f8ed
6/5/2025 Umm Al Quwain Meter
bc799e76df518aef63fc30f6fd714233ede021d0d358917705669a72736fdd6d
bc799e76df518aef63fc30f6fd714233ede021d0d358917705669a72736fdd6d
6/4/2025 Umm Al Quwain Meter
d1deef9abd7aaa5da7779881677642ac0fd493a8f1009e773044f62425ccbc9c
d1deef9abd7aaa5da7779881677642ac0fd493a8f1009e773044f62425ccbc9c
6/3/2025 Umm Al Quwain Meter
bc5736d9be9e41eba904e8e03e03fc0aab2cb2ae34b7f6429d5639696d5463e1
bc5736d9be9e41eba904e8e03e03fc0aab2cb2ae34b7f6429d5639696d5463e1
6/2/2025 Umm Al Quwain Meter
c774818c2021839cfec315dc0aad9689ca1286e07cdc61b67b445b078bc0f2fc
c774818c2021839cfec315dc0aad9689ca1286e07cdc61b67b445b078bc0f2fc
6/1/2025 Umm Al Quwain Meter
a0fc6c870baeaa43f185cd05764677f7d7418e442fd84c2a0177d6380cbdc333
a0fc6c870baeaa43f185cd05764677f7d7418e442fd84c2a0177d6380cbdc333
5/31/2025 Umm Al Quwain Meter
6ca17cb9c1d22b6ddbe5345628e6181fdcad49a137959121226f35ab22ef5a08
6ca17cb9c1d22b6ddbe5345628e6181fdcad49a137959121226f35ab22ef5a08
Factores Exante
Owner Token Start End Validity Value Unit Status Archives User
Owner Token Start End Validity Value Unit Status Archives User
UAQ-WD H2O 1/1/2023 12/31/2034 Válido 1 m³CO2/m³ Approved
cmosella@energylab.cl
Constants
There are no registered constants.
First you must create a constant to visualize it.
Factores Exante
Owner Token Start End Validity Value Unit Status Archives User
Owner Token Start End Validity Value Unit Status Archives User
UAQ-WD H2O 1/1/2023 12/31/2034 Válido 1 m³CO2/m³ Approved
cmosella@energylab.cl
Constants
There are no registered constants.
First you must create a constant to visualize it.